Christopher J. Igneri Playground Reconstruction (RG-214MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and basketball court at Christopher J. Igneri Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2014
Projected Completion Date: March 2014
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: July 2016

Construction

Start Date: September 2016
Projected Completion Date: September 2018
Completion Date: September 2017

Understand how we build parks.

Funding

Total Funding: $620,000
Funding Source: Mayoral

Location

Christopher J. Igneri Playground, Staten Island
Schmidts Lane & Manor Road
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024