Staten Island General Site Work (RG-1013M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball courts, pavements, fencing, safety surfacing, timber barrier rails and landscaping elements at various sites in Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2012
Projected Completion Date: May 2013
Completion Date: July 2013

Procurement

Start Date: July 2013
Projected Completion Date: April 2014
Completion Date: July 2015

Construction

Start Date: July 2015
Projected Completion Date: July 2017
Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $1,293,000
Funding Sources:
  • City Council
  • Mayoral

Locations

  • CPL. Thompson Park, Staten Island
    Broadway, Henderson Ave., Chappell St.
    Community Board: 01
  • Gerard P. Dugan Playground, Staten Island
    Mill Rd. to Weed Ave. between Tysens La. and Isernia Ave.
    Community Board: 03
  • Greencroft Playground, Staten Island
    Greencroft Ave. between Ainsworth Ave. and Redgrave Ave.
    Community Board: 03
  • Wolfe's Pond Park, Staten Island
    Holton Ave., Chisolm St., Luten Ave., Arbutus Ave. and Raritan Bay
    Community Board: 03
 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024