Staten Island General Site Work (RG-1013M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball courts, pavements, fencing, safety surfacing, timber barrier rails and landscaping elements at various sites in Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2012
Projected Completion Date:
May 2013
Completion Date:
July 2013
Procurement
Start Date: July 2013
Projected Completion Date:
April 2014
Completion
Date:
July 2015
Construction
Start Date: July 2015
Projected Completion Date:
July 2017
Completion Date: December 2016
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Locations
-
CPL. Thompson Park, Staten Island
Broadway, Henderson Ave., Chappell St.
Community Board: 01 -
Gerard P. Dugan Playground, Staten Island
Mill Rd. to Weed Ave. between Tysens La. and Isernia Ave.
Community Board: 03 -
Greencroft Playground, Staten Island
Greencroft Ave. between Ainsworth Ave. and Redgrave Ave.
Community Board: 03 -
Wolfe's Pond Park, Staten Island
Holton Ave., Chisolm St., Luten Ave., Arbutus Ave. and Raritan Bay
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024