Queens General Site Work (QG-1313M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Frank O'Connor Playground, Crowley Playground, and Real Good Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2013
Projected Completion Date:
August 2013
Completion Date:
October 2014
Procurement
Start Date: October 2014
Projected Completion Date:
July 2015
Completion
Date:
July 2015
Construction
Start Date: November 2015
Projected Completion Date:
May 2017
Completion Date: February 2018
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Locations
-
Crowley Playground, Queens
Queens Midtown Exwy., 57 Ave. bet. 84 St. and 82 St.
Community Board: 04 -
Frank D. O'Connor Playground, Queens
Broadway, Woodside Ave. bet. 77 St. and Baxter Ave.
Community Board: 04 -
Real Good Playground, Queens
Horace Harding Exwy. Sr. Rd. S., 62 Ave. bet. 99 St. and 102 St.
Community Board: 06
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025