Queens General Site Work (QG-1313M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Frank O'Connor Playground, Crowley Playground, and Real Good Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2013
Projected Completion Date: August 2013
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: July 2015

Construction

Start Date: November 2015
Projected Completion Date: May 2017
Completion Date: February 2018

Understand how we build parks.

Funding

Total Funding: $1,925,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025