Queens General Site Work (QG-913M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct pavements, drainage, plantings, safety surface and general site work in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2013
Projected Completion Date: May 2013
Completion Date: August 2013

Procurement

Start Date: August 2013
Projected Completion Date: May 2014
Completion Date: June 2014

Construction

Start Date: September 2014
Projected Completion Date: March 2016
Completion Date: July 2015

Understand how we build parks.

Funding

Total Funding: $943,000
Funding Source: Borough President

Locations

  • Highland Park, Queens
    Highland Boulevard, Jamaica Avenue, Jackie Robinson Parkway
    Community Board: 05, 05
  • Holy Cow Playground, Queens
    Peck Avenue & Harding Boulevard
    Community Board: 08
 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025