Queens General Site Work (QG-913M)
-
100% complete
-
100% complete
-
100% complete
This multisite contract will reconstruct pavements, drainage, plantings, safety surface and general site work in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2013
Projected Completion Date:
May 2013
Completion Date:
August 2013
Procurement
Start Date: August 2013
Projected Completion Date:
May 2014
Completion
Date:
June 2014
Construction
Start Date: September 2014
Projected Completion Date:
March 2016
Completion Date: July 2015
Understand how we build parks.
Funding
Funding Source: Borough President
Locations
-
Highland Park, Queens
Highland Boulevard, Jamaica Avenue, Jackie Robinson Parkway
Community Board: 05, 05 -
Holy Cow Playground, Queens
Peck Avenue & Harding Boulevard
Community Board: 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025