Staten Island General Site Work (RG-713M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct play equipment, safety surfacing, play fields, pavements, fencing, plantings and general site work at various sites in Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2012
Projected Completion Date: March 2013
Completion Date: March 2013

Procurement

Start Date: March 2013
Projected Completion Date: December 2013
Completion Date: September 2013

Construction

Start Date: October 2013
Projected Completion Date: April 2015
Completion Date: March 2015

Understand how we build parks.

Funding

Total Funding: $1,889,000
Funding Sources:
  • Federal
  • Mayoral

Locations

  • Conference House Park, Staten Island
    Shore Road, Satterlee Street, Massachusetts, Surf, Billop Avenues, Brighton Street
    Community Board: 03
  • Franklin D. Roosevelt Boardwalk and Beach, Staten Island
    Between Graham Boulevard, Jefferson Avenue, Father Capodanno Boulevard
    Community Board: 02
  • Great Kills Park, Staten Island
    Hylan, Fairlawn to Emmet, Cedar Grove to New Dorp.
    Community Board: 03
  • Lemon Creek Park, Staten Island
    Hylan Blvd. from Sharrott Ave. to Seguine Ave.
    Community Board: 03
  • Silver Lake Park, Staten Island
    Victory Blvd., Clove Rd., Forest Ave.
    Community Board: 01
 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024