Tiffany Street Pier Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the fishing pier that was damaged by Hurricane Sandy.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2013
Projected Completion Date: March 2015
Completion Date: October 2015

Procurement

Start Date: October 2015
Projected Completion Date: July 2016
Completion Date: March 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $2,111,000
Funding Sources:
  • Federal
  • Mayoral

Location

Tiffany Street Pier, Bronx
Tiffany Street pier located at East river and intersection Tiffany Street and Viele Avenue, Bronx N.Y.
Community Board: 02

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024