Shoelace Park Green Infrastructure Construction Phase 1
-
100% complete
-
100% complete
-
100% complete
This project will construct green infrastructure to capture storm water and stabilize hillsides and slopes at Shoelace Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2012
Projected Completion Date:
June 2014
Completion Date:
February 2016
Procurement
Start Date: February 2016
Projected Completion Date:
November 2016
Completion
Date:
March 2017
Construction
Start Date: July 2017
Projected Completion Date:
July 2018
Completion Date: July 2018
Understand how we build parks.
Funding
Funding Source: Federal
Location
Bronx River Parkway, Bronx
Bronx Boulevard between East 227th and East 228th Streets
Community Board: 06, 09, 12
Project Staff
Contact NYC Parks about this projectLast updated: 01/17/2025