Shoelace Park Green Infrastructure Construction Phase 1

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct green infrastructure to capture storm water and stabilize hillsides and slopes at Shoelace Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2012
Projected Completion Date: June 2014
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: November 2016
Completion Date: March 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $357,000
Funding Source: Federal

Location

Bronx River Parkway, Bronx
Bronx Boulevard between East 227th and East 228th Streets
Community Board: 06, 09, 12

 

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025