Tony Dapolito Recreation Center and John Jay Pool Boiler Systems Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct boiler components damaged by Hurricane Sandy at Tony Dapolito Recreation Center and John Jay Pool.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2012
Projected Completion Date:
February 2013
Completion Date:
March 2013
Procurement
Start Date: March 2013
Projected Completion Date:
December 2013
Completion
Date:
May 2014
Construction
Start Date: June 2014
Projected Completion Date:
June 2015
Completion Date: February 2015
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Locations
-
John Jay Park, Manhattan
East 76-East 78 Streets, Cherokee Place
Community Board: 08 -
Tony Dapolito Recreation Center, Manhattan
Carmine St. and Clarkson St., 7 Ave.
Community Board: 02
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025