Heritage Park Operations Building Demolition (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will demolish the operations building at Heritage Park (Blissenbach Marina), which was damaged by Hurricane Sandy.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2013
Completion Date:
February 2014
Procurement
Start Date: February 2014
Projected Completion Date:
October 2014
Completion
Date:
April 2016
Construction
Start Date: September 2016
Projected Completion Date:
September 2017
Completion Date: October 2017
Understand how we build parks.