Manhattan General Site Work (MG-213M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct pavements, fences, plantings, plumbing and general site work in Manhattan.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2013
Projected Completion Date:
May 2014
Completion Date:
June 2014
Procurement
Start Date: June 2014
Projected Completion Date:
March 2015
Completion
Date:
June 2015
Construction
Start Date: June 2015
Projected Completion Date:
December 2016
Completion Date: December 2016
Understand how we build parks.
Funding
Funding Source: City Council
Locations
-
De Witt Clinton Park, Manhattan
W. 52 St. To W. 54 St., 11 Ave. To 12 Ave.
Community Board: 04 -
Hell's Kitchen Park, Manhattan
10 Ave., W. 47 St. To W. 48 St.
Community Board: 04 -
Septuagesimo UNO, Manhattan
71 St. Between West End Ave. and Amsterdam Ave.
Community Board: 07 -
Orchard Alley Garden, Manhattan
E. 4 St. bet. Ave. C and Ave. D
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025