Manhattan General Site Work (MG-213M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavements, fences, plantings, plumbing and general site work in Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2013
Projected Completion Date: May 2014
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date: March 2015
Completion Date: June 2015

Construction

Start Date: June 2015
Projected Completion Date: December 2016
Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $1,059,000
Funding Source: City Council

Locations

  • De Witt Clinton Park, Manhattan
    W. 52 St. To W. 54 St., 11 Ave. To 12 Ave.
    Community Board: 04
  • Hell's Kitchen Park, Manhattan
    10 Ave., W. 47 St. To W. 48 St.
    Community Board: 04
  • Septuagesimo UNO, Manhattan
    71 St. Between West End Ave. and Amsterdam Ave.
    Community Board: 07
  • Orchard Alley Garden, Manhattan
    E. 4 St. bet. Ave. C and Ave. D
 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025