CS 134 Community Garden Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the perimeter concrete retaining walls, steel fencing and gate, and install a new water supply system at CS 134 Community Garden.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2017
Projected Completion Date:
July 2017
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
March 2019
Completion
Date:
March 2019
Construction
Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date: June 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Bristow Street between Freeman and Jennings Streets
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024