CS 134 Community Garden Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the perimeter concrete retaining walls, steel fencing and gate, and install a new water supply system at CS 134 Community Garden.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2017
Projected Completion Date: July 2017
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: March 2019

Construction

Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $1,015,000
Funding Sources:
  • City Council
  • Mayoral

Location

Bristow Street between Freeman and Jennings Streets

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024