Marine Park Gerritsen Avenue Pedestrian Path Construction Phase 1

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct new asphalt paths along Gerritsen Avenue and provide improved accessibility to the existing baseball fields in Marine Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: June 2015
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: June 2016

Construction

Start Date: August 2016
Projected Completion Date: August 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $480,000
Funding Sources:
  • City Council
  • Mayoral

Location

Marine Park, Brooklyn
Gerritsen Avenue between Seba Avenue and Florence Avenue
Community Board: 15, 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024