Marine Park Gerritsen Avenue Pedestrian Path Construction Phase 1
-
100% complete
-
100% complete
-
100% complete
This project will construct new asphalt paths along Gerritsen Avenue and provide improved accessibility to the existing baseball fields in Marine Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2015
Projected Completion Date:
June 2015
Completion Date:
September 2015
Procurement
Start Date: September 2015
Projected Completion Date:
June 2016
Completion
Date:
June 2016
Construction
Start Date: August 2016
Projected Completion Date:
August 2017
Completion Date: April 2017
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Marine Park, Brooklyn
Gerritsen Avenue between Seba Avenue and Florence Avenue
Community Board: 15, 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024