Soundview Park Dog Run Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a dog run in Soundview Park in the Bronx.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2013
Projected Completion Date: June 2014
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: May 2015

Construction

Start Date: July 2015
Projected Completion Date: July 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $347,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Soundview Park, Bronx
Lafayette Avenue between Colgate and Boynton Avenues
Community Board: 09

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024