Red Hook Recreation Center Sandy-Related Emergency Boiler Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the boiler at Red Hook Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2012
Completion Date:
February 2013
Procurement
Start Date: February 2013
Projected Completion Date:
November 2013
Completion
Date:
July 2013
Construction
Start Date: June 2013
Projected Completion Date:
October 2013
Completion Date: June 2014
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Red Hook Recreation Area, Brooklyn
Bay Street between Clinton Street and Henry Street
Community Board: 06
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025