Queens Green Infrastructure Construction (QG-813M)
-
100% complete
-
100% complete
-
100% complete
This project will prepare beds and create bioswales for stormwater capture at various locations in Community Boards 4-6 and 9 in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2013
Projected Completion Date:
March 2013
Completion Date:
March 2013
Procurement
Start Date: March 2013
Projected Completion Date:
December 2013
Completion
Date:
February 2014
Construction
Start Date: October 2014
Projected Completion Date:
October 2015
Completion Date: September 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024