Queens Green Infrastructure Construction (QG-813M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will prepare beds and create bioswales for stormwater capture at various locations in Community Boards 4-6 and 9 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2013
Projected Completion Date: March 2013
Completion Date: March 2013

Procurement

Start Date: March 2013
Projected Completion Date: December 2013
Completion Date: February 2014

Construction

Start Date: October 2014
Projected Completion Date: October 2015
Completion Date: September 2016

Understand how we build parks.

Funding

Total Funding: $2,305,000
Funding Source: Mayoral

Location

Various locations in Queens