Seton Park Ballfields Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the ballfields with synthetic turf at Seton Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: September 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: July 2018

Construction

Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $1,696,000
Funding Sources:
  • City Council
  • State

Location

Seton Park, Bronx
Independence Avenue and West 235 Street
Community Board: 08

 