Crotona Park Ballfield 5 Synthetic Turf Field Construction
-
100% complete
-
100% complete
-
100% complete
This project will demolish softball field 5 at Crotona Park and construct a synthetic turf soccer field.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2016
Projected Completion Date:
April 2017
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
June 2018
Construction
Start Date: August 2018
Projected Completion Date:
August 2019
Completion Date: December 2022
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Crotona Park, Bronx
Crotona Park North and Crotona Avenue
Community Board: 03
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024