Crotona Park Ballfield 1 Lighting Installation
-
100% complete
-
100% complete
-
100% complete
This project will construct sports lighting at ballfield 1 in Crotona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2015
Projected Completion Date:
June 2016
Completion Date:
June 2016
Procurement
Start Date: June 2016
Projected Completion Date:
March 2017
Completion
Date:
December 2017
Construction
Start Date: February 2018
Projected Completion Date:
February 2019
Completion Date: July 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Crotona Park, Bronx
Crotona Park East between Claremont Parkway and Crotona Avenue
Community Board: 03
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025