Parque de los Ninos Playground and Seating Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and seating area at Parque de los Ninos.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2013
Projected Completion Date: June 2015
Completion Date: July 2015

Procurement

Start Date: July 2015
Projected Completion Date: April 2016
Completion Date: September 2016

Construction

Start Date: August 2016
Projected Completion Date: July 2017
Completion Date: March 2017

Understand how we build parks.

Funding

Total Funding: $1,417,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Bronx River Parkway, Bronx
Morrison Avenue and Watson Avenue
Community Board: 06, 09, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025