Parque de los Ninos Playground and Seating Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground and seating area at Parque de los Ninos.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2013
Projected Completion Date:
June 2015
Completion Date:
July 2015
Procurement
Start Date: July 2015
Projected Completion Date:
April 2016
Completion
Date:
September 2016
Construction
Start Date: August 2016
Projected Completion Date:
July 2017
Completion Date: March 2017
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Location
Bronx River Parkway, Bronx
Morrison Avenue and Watson Avenue
Community Board: 06, 09, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025