St. Mary's Park and Recreation Center Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct rain gardens and other green infrastructure to capture storm water at St. Mary's Park in the Bronx.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2014
Projected Completion Date: May 2015
Completion Date: September 2017

Procurement

Start Date: September 2017
Projected Completion Date: June 2018
Completion Date: November 2018

Construction

Start Date: January 2019
Projected Completion Date: January 2020
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $1,207,000
Funding Sources:
  • Mayoral
  • State

Location

St. Mary's Park, Bronx
St. Anns Avenue between East 145th and East 146th Streets
Community Board: 01

 

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024