St. Mary's Park and Recreation Center Green Infrastructure Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct rain gardens and other green infrastructure to capture storm water at St. Mary's Park in the Bronx.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2014
Projected Completion Date:
May 2015
Completion Date:
September 2017
Procurement
Start Date: September 2017
Projected Completion Date:
June 2018
Completion
Date:
November 2018
Construction
Start Date: January 2019
Projected Completion Date:
January 2020
Completion Date: October 2019
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
St. Mary's Park, Bronx
St. Anns Avenue between East 145th and East 146th Streets
Community Board: 01
Project Staff
Contact NYC Parks about this projectLast updated: 01/17/2025