Project Timeline
Design
Assigned & Start Date: February 2012
Projected Completion Date:
May 2013
Completion Date:
July 2013
Procurement
Start Date: July 2013
Projected Completion Date:
April 2014
Completion
Date:
July 2014
Construction
Start Date: September 2014
Projected Completion Date:
September 2015
Completion Date: July 2015
Understand how we build parks.
Funding
Funding Source: City Council
Location
Flushing Meadows Corona Park, Queens
Avenue of Commerce and Herbert Hoover Promenade
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024