Forest Park T-Ball Field and The Overlook Drainage System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the paths, drainage and the T-ball field in Forest Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2013
Projected Completion Date: November 2013
Completion Date: February 2014

Procurement

Start Date: February 2014
Projected Completion Date: November 2014
Completion Date: January 2015

Construction

Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $1,279,000
Funding Sources:
  • Borough President
  • City Council

Location

Forest Park, Queens
Park Lane between Union Turnpike and Park Lane South, Queens
Community Board: 05, 05, 06, 09

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024