Staten Island Clean-Up and Safe-Up of Beaches and Parks (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install emergency chain link fencing, remove debris and sand, and demolish unsafe structures. This project will also include services of a bathymetric surveyor necessary for the opening of the swimmable beaches.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2012
Completion Date: January 2013

Procurement

Start Date: January 2013
Projected Completion Date: October 2013
Completion Date: March 2013

Construction

Start Date: February 2013
Projected Completion Date: August 2013
Completion Date: July 2013

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral