Queens General Site Work (QG-713MA)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct pavements, fencing, plantings, and benches in at various parks in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2013
Projected Completion Date:
March 2013
Completion Date:
March 2014
Procurement
Start Date: March 2014
Projected Completion Date:
December 2014
Completion
Date:
March 2015
Construction
Start Date: May 2015
Projected Completion Date:
November 2016
Completion Date: November 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Alley Pond Park, Queens
Little Neck Bay to Springfield Boulevard, Union Turnpike
Community Board: 11 -
Fort Totten Park, Queens
Fort Totten, Cross Island Parkway, Totten Road to 15 Road
Community Board: 07 -
Judge Moses Weinstein Playground, Queens
Vleigh Place & 141 Street
Community Board: 08 -
Police Officer Nicholas Demutiis Park, Queens
Liberty Avenue & 102nd Street
Community Board: 10 -
Highland Park Childrens Garden, Brooklyn
Jamaica Avenue, Warwick Street, Force Tube Avenues