Queens General Site Work (QG-613M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct play equipment, pavements, fencing, and plantings in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2013
Projected Completion Date: March 2013
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date: March 2015
Completion Date: May 2015

Construction

Start Date: July 2015
Projected Completion Date: January 2017
Completion Date: November 2016

Understand how we build parks.

Funding

Total Funding: $1,827,000
Funding Source: Mayoral

Locations

  • Alley Athletic Playground, Queens
    Grand Central Parkway, Union Turnpike, Winchester Boulevard
    Community Board: 13
  • Brookville Park, Queens
    149 Avenue, 235 Street, Brookville Boulevard, South Conduit Avenue
    Community Board: 13
  • Elmhurst Park, Queens
    Grand Ave., 57 Ave. bet. 74 St. and 80 St.
    Community Board: 04
  • Forest Park, Queens
    Myrtle Avenue, Woodhaven Boulevard
    Community Board: 05, 05, 06, 09
  • Highland Park, Queens
    Jamaica Avenue & Elton Street
    Community Board: 05, 05
  • Rufus King Park, Queens
    Jamaica Ave., 89 Ave. bet. 150 St. and 153 St.
    Community Board: 12
 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024