Queens General Site Work (QG-613M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct play equipment, pavements, fencing, and plantings in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2013
Projected Completion Date:
March 2013
Completion Date:
June 2014
Procurement
Start Date: June 2014
Projected Completion Date:
March 2015
Completion
Date:
May 2015
Construction
Start Date: July 2015
Projected Completion Date:
January 2017
Completion Date: November 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Alley Athletic Playground, Queens
Grand Central Parkway, Union Turnpike, Winchester Boulevard
Community Board: 13 -
Brookville Park, Queens
149 Avenue, 235 Street, Brookville Boulevard, South Conduit Avenue
Community Board: 13 -
Elmhurst Park, Queens
Grand Ave., 57 Ave. bet. 74 St. and 80 St.
Community Board: 04 -
Forest Park, Queens
Myrtle Avenue, Woodhaven Boulevard
Community Board: 05, 05, 06, 09 -
Highland Park, Queens
Jamaica Avenue & Elton Street
Community Board: 05, 05 -
Rufus King Park, Queens
Jamaica Ave., 89 Ave. bet. 150 St. and 153 St.
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024