Manhattan Beach Dog Run Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the existing dog run to provide separate dog runs for both small and large dogs with new surface materials, drinking fountains for both dogs and their owners, and seating at Manhattan Beach Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: July 2018
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020
Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $787,000
Funding Sources:
  • City Council
  • Mayoral

Location

Manhattan Beach Park, Brooklyn
Oriental Boulevard at Kensington Street
Community Board: 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024