Beaver Noll Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct Beaver Noll Park, which will include a tot lot and sitting area.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2012
Projected Completion Date:
December 2015
Completion Date:
February 2017
Procurement
Start Date: February 2017
Projected Completion Date:
November 2017
Completion
Date:
May 2018
Construction
Start Date: June 2018
Projected Completion Date:
June 2019
Completion Date: June 2019