Shore Parkway Emergency Protective Measures (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will construct emergency public safely measures, including but limited to, fencing, paving, walls, demolitions, structural supports and site access.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2012
Completion Date:
January 2013
Procurement
Start Date: January 2013
Projected Completion Date:
October 2013
Completion
Date:
May 2013
Construction
Start Date: February 2013
Projected Completion Date:
July 2013
Completion Date: November 2013
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Belt Parkway/Shore Parkway, Brooklyn
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024