Shore Parkway Emergency Protective Measures (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct emergency public safely measures, including but limited to, fencing, paving, walls, demolitions, structural supports and site access.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2012
Completion Date: January 2013

Procurement

Start Date: January 2013
Projected Completion Date: October 2013
Completion Date: May 2013

Construction

Start Date: February 2013
Projected Completion Date: July 2013
Completion Date: November 2013

Understand how we build parks.

Funding

Total Funding: $2,195,000
Funding Sources:
  • Federal
  • Mayoral

Location

Belt Parkway/Shore Parkway, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project