Rockaway Beach Emergency Protective Measures (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct immediate public safety measures, including but not limited to fencing, walls, demolition/structural supports and site access, at Rockaway Beach.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2012
Completion Date: January 2013

Procurement

Start Date: January 2013
Projected Completion Date: October 2013
Completion Date: April 2013

Construction

Start Date: February 2013
Projected Completion Date: June 2013
Completion Date: November 2013

Understand how we build parks.

Funding

Total Funding: $8,810,000
Funding Sources:
  • Federal
  • Mayoral

Location

Rockaway Beach and Boardwalk, Queens
Beach 9th Street to Beach 149th Street
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024