Rockaway Beach Emergency Protective Measures (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will construct immediate public safety measures, including but not limited to fencing, walls, demolition/structural supports and site access, at Rockaway Beach.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2012
Completion Date:
January 2013
Procurement
Start Date: January 2013
Projected Completion Date:
October 2013
Completion
Date:
April 2013
Construction
Start Date: February 2013
Projected Completion Date:
June 2013
Completion Date: November 2013
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Rockaway Beach and Boardwalk, Queens
Beach 9th Street to Beach 149th Street
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project