Brooklyn and Staten Island Sidewalk Reconstruction FY13
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct damaged sidewalks in Brooklyn and Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2012
Projected Completion Date:
June 2013
Completion Date:
December 2012
Procurement
Start Date: December 2012
Projected Completion Date:
September 2013
Completion
Date:
December 2014
Construction
Start Date: April 2015
Projected Completion Date:
April 2016
Completion Date: January 2016
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Various locations, Brooklyn and Staten Island
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024