Mathews-Palmer Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Mathews-Palmer Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2013
Projected Completion Date: September 2014
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: February 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $2,385,000
Funding Source: City Council

Location

Mathews-Palmer Playground, Manhattan
West 45th Street between 9th and 10th Avenues, Manhattan
Community Board: 04

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025