Mathews-Palmer Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Mathews-Palmer Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2013
Projected Completion Date:
September 2014
Completion Date:
July 2016
Procurement
Start Date: July 2016
Projected Completion Date:
April 2017
Completion
Date:
February 2017
Construction
Start Date: April 2017
Projected Completion Date:
April 2018
Completion Date: April 2018
Understand how we build parks.
Funding
Funding Source: City Council
Location
Mathews-Palmer Playground, Manhattan
West 45th Street between 9th and 10th Avenues, Manhattan
Community Board: 04
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025