Elizabeth H. Berger Plaza Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct Elizabeth H. Berger Plaza, closing the slip road between two smaller parks to create one larger plaza with plantings, a lawn mound, and seating.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2012
Projected Completion Date:
September 2015
Completion Date:
March 2018
Procurement
Start Date: March 2018
Projected Completion Date:
December 2018
Completion
Date:
April 2019
Construction
Start Date: August 2019
Projected Completion Date:
August 2020
Completion Date: January 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Trinity Place, Greenwich Street, Morris Street and Egdar Street
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025