John Allen Payne Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play area to include new play equipment, swings, and spray shower area at John Allen Payne Playground

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2014
Projected Completion Date: November 2015
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: January 2017
Completion Date: February 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $2,449,000
Funding Source: City Council

Location

John Allen Payne Playground, Brooklyn
3rd Avenue between 64th Street and 65th Street
Community Board: 07

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/21/2025