John Allen Payne Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play area to include new play equipment, swings, and spray shower area at John Allen Payne Playground
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2014
Projected Completion Date:
November 2015
Completion Date:
April 2016
Procurement
Start Date: April 2016
Projected Completion Date:
January 2017
Completion
Date:
February 2017
Construction
Start Date: April 2017
Projected Completion Date:
April 2018
Completion Date: July 2018
Understand how we build parks.
Funding
Funding Source: City Council
Location
John Allen Payne Playground, Brooklyn
3rd Avenue between 64th Street and 65th Street
Community Board: 07
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 02/21/2025