Veterans Grove Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Veterans Grove.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2013
Projected Completion Date: November 2013
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: June 2016

Construction

Start Date: June 2016
Projected Completion Date: December 2017
Completion Date: February 2017

Understand how we build parks.

Funding

Total Funding: $1,951,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Veterans Grove, Queens
43rd Avenue, Judge Street and Whitney Avenue
Community Board: 04

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024