Veterans Grove Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Veterans Grove.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2013
Projected Completion Date:
November 2013
Completion Date:
June 2015
Procurement
Start Date: June 2015
Projected Completion Date:
March 2016
Completion
Date:
June 2016
Construction
Start Date: June 2016
Projected Completion Date:
December 2017
Completion Date: February 2017