St. James Recreation Center HVAC Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the boiler, heating and air conditioning systems at St. James Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2012
Projected Completion Date:
August 2013
Completion Date:
September 2017
Procurement
Start Date: September 2017
Projected Completion Date:
June 2018
Completion
Date:
October 2018
Construction
Start Date: January 2019
Projected Completion Date:
January 2020
Completion Date: January 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
St. James Park, Bronx
Jerome Avenue between East 190th Street and East 193rd Street
Community Board: 07
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project