St. James Recreation Center HVAC Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the boiler, heating and air conditioning systems at St. James Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2012
Projected Completion Date: August 2013
Completion Date: September 2017

Procurement

Start Date: September 2017
Projected Completion Date: June 2018
Completion Date: October 2018

Construction

Start Date: January 2019
Projected Completion Date: January 2020
Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $1,675,000
Funding Source: Mayoral

Location

St. James Park, Bronx
Jerome Avenue between East 190th Street and East 193rd Street
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024