Mary Whalen Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Mary Whalen Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2013
Projected Completion Date: August 2013
Completion Date: July 2014

Procurement

Start Date: July 2014
Projected Completion Date: April 2015
Completion Date: June 2015

Construction

Start Date: July 2015
Projected Completion Date: July 2016
Completion Date: May 2016

Understand how we build parks.

Funding

Total Funding: $1,349,000
Funding Sources:
  • City Council
  • Mayoral

Location

Forest Park, Queens
79th Street and Park Lane South, Queens
Community Board: 05, 05, 06, 09

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024