MacNeil Park Esplanade Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the esplanade in MacNeil Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2013
Projected Completion Date:
June 2015
Completion Date:
December 2016
Procurement
Start Date: December 2016
Projected Completion Date:
September 2017
Completion
Date:
November 2017
Construction
Start Date: February 2018
Projected Completion Date:
August 2019
Completion Date: May 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Hermon A. MacNeil Park, Queens
Poppenhusen Avenue, East River, 115th Street, College Place
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025