MacNeil Park Esplanade Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the esplanade in MacNeil Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2013
Projected Completion Date: June 2015
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: November 2017

Construction

Start Date: February 2018
Projected Completion Date: August 2019
Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $4,045,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Hermon A. MacNeil Park, Queens
Poppenhusen Avenue, East River, 115th Street, College Place
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025