Baisley Pond Park Pathway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct paths in Baisley Pond Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2013
Projected Completion Date: June 2014
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: April 2015

Construction

Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: May 2016

Understand how we build parks.

Funding

Total Funding: $1,198,000
Funding Source: City Council

Location

Baisley Pond Park, Queens
119th Avenue and Lake View Boulevard East to 155th Street and 122nd Avenue, Queens
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024