DeSalvio Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct DeSalvio Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2013
Projected Completion Date: June 2015
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: December 2016

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $1,740,000
Funding Sources:
  • Borough President
  • City Council

Location

DeSalvio Playground, Manhattan
Mulberry and Spring Streets
Community Board: 02

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024