DeSalvio Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct DeSalvio Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2013
Projected Completion Date:
June 2015
Completion Date:
September 2015
Procurement
Start Date: September 2015
Projected Completion Date:
June 2016
Completion
Date:
December 2016
Construction
Start Date: July 2017
Projected Completion Date:
July 2018
Completion Date: February 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
DeSalvio Playground, Manhattan
Mulberry and Spring Streets
Community Board: 02
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project