Riverside Park South Natural Turf Ballfield & Greenway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the natural turf ballfield and greenway paths in Riverside Park South.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2013
Projected Completion Date: October 2014
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: August 2019
Completion Date: April 2020

Construction

Start Date: September 2020
Projected Completion Date: March 2022
Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $7,023,000
Funding Sources:
  • City Council
  • Mayoral

Location

Riverside Park South, Manhattan
Hudson River between West 59th Street and West 72nd Street
Community Board: 07

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024