Riverside Park South Natural Turf Ballfield & Greenway Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the natural turf ballfield and greenway paths in Riverside Park South.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2013
Projected Completion Date:
October 2014
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
August 2019
Completion
Date:
April 2020
Construction
Start Date: September 2020
Projected Completion Date:
March 2022
Completion Date: June 2022
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Riverside Park South, Manhattan
Hudson River between West 59th Street and West 72nd Street
Community Board: 07
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024