McKinley Park and Seth Low Playground Synthetic Turf Field Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct new synthetic turf fields at McKinley Park and Seth Low Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2012
Projected Completion Date: December 2014
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: May 2016
Completion Date: June 2016

Construction

Start Date: September 2016
Projected Completion Date: March 2018
Completion Date: September 2017

Understand how we build parks.

Funding

Total Funding: $4,142,000
Funding Sources:
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project