Hickman Playground and Harry Maze Playground Multipurpose Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the multi-purpose ballfields at Hickman Playground and Harry Maze Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2012
Projected Completion Date:
February 2013
Completion Date:
August 2014
Procurement
Start Date: August 2014
Projected Completion Date:
May 2015
Completion
Date:
May 2015
Construction
Start Date: July 2015
Projected Completion Date:
July 2016
Completion Date: August 2016
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Locations
-
Harry Maze Playground, Brooklyn
Ave. D, Ditmas Ave. bet. E. 56 St. and E. 57 St.
Community Board: 17 -
Hickman Playground, Brooklyn
Veterans Av Bet E 68 and E 66 Sts
Community Board: 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025