Lindower Park Ballfield Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the natural turf ballfields in Lindower Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2012
Projected Completion Date: November 2013
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: May 2015

Construction

Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: December 2015

Understand how we build parks.

Funding

Total Funding: $1,578,000
Funding Sources:
  • Borough President
  • City Council

Location

Lindower Park, Brooklyn
Strickland Avenue, East 60th Street and Mill Avenue, Brooklyn
Community Board: 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024