Wolfe's Pond Park Landscape Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the berm and restore the landscape in Wolfe's Pond Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2013
Projected Completion Date: June 2014
Completion Date: October 2015

Procurement

Start Date: October 2015
Projected Completion Date: July 2016
Completion Date: June 2017

Construction

Start Date: October 2017
Projected Completion Date: September 2019
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $2,948,000
Funding Sources:
  • Federal
  • Mayoral
  • State

Location

Wolfe's Pond Park, Staten Island
Holton Avenue and Purdy Place
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024