Bronx and Queens Reforestation FY10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will plant new and replacement trees in the Bronx and Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2012
Projected Completion Date: January 2013
Completion Date: December 2012

Procurement

Start Date: December 2012
Projected Completion Date: September 2013
Completion Date: February 2013

Construction

Start Date: March 2013
Projected Completion Date: June 2015
Completion Date: May 2015

Understand how we build parks.

Funding

Total Funding: $733,000
Funding Source: Mayoral

Location

Various locations in the Bronx and Queens.

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025