Asser Levy Playground Expansion

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will expand Asser Levy Playground into the roadbed of Asser Levy Place and construct a new artificial turf field and exercise track, new adult fitness equipment, benches, tables, drinking fountains, park lighting and trees.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2012
Projected Completion Date: February 2013
Completion Date: May 2013

Procurement

Start Date: May 2013
Projected Completion Date: February 2014
Completion Date: September 2013

Construction

Start Date: October 2013
Projected Completion Date: October 2014
Completion Date: October 2014

Understand how we build parks.

Funding

Total Funding: $1,293,000
Funding Sources:
  • City Council
  • Private

Location

Asser Levy Playground, Manhattan
Asser Levy Place between East 23rd Street and East 25th Street
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024