Asser Levy Playground Expansion
-
100% complete
-
100% complete
-
100% complete
This project will expand Asser Levy Playground into the roadbed of Asser Levy Place and construct a new artificial turf field and exercise track, new adult fitness equipment, benches, tables, drinking fountains, park lighting and trees.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2012
Projected Completion Date:
February 2013
Completion Date:
May 2013
Procurement
Start Date: May 2013
Projected Completion Date:
February 2014
Completion
Date:
September 2013
Construction
Start Date: October 2013
Projected Completion Date:
October 2014
Completion Date: October 2014
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Private
Location
Asser Levy Playground, Manhattan
Asser Levy Place between East 23rd Street and East 25th Street
Community Board: 06
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024