Astoria Park Diving Pool Plaza Construction
-
100% complete
-
100% complete
-
100% complete
This project will demolish the diving pool at the Astoria Park Bathhouse and construct a plaza in its place.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2012
Projected Completion Date:
October 2013
Completion Date:
December 2016
Procurement
Start Date: December 2016
Projected Completion Date:
September 2017
Completion
Date:
November 2017
Construction
Start Date: November 2017
Projected Completion Date:
November 2019
Completion Date: November 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Astoria Park, Queens
24-02 19th Street, between 23rd Street and 23rd Drive
Community Board: 01
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024