Citywide Green Infrastructure Construction FY13

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will construct green infrastructure elements at citywide locations.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2013
Projected Completion Date: April 2013
Completion Date: May 2013

Procurement

Start Date: May 2013
Projected Completion Date: February 2014
Completion Date: January 2014

Construction

Start Date: May 2014
Projected Completion Date: April 2015
Completion Date: December 2015