Wyckoff House Park Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a public restroom building in Wyckoff House Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2017
Projected Completion Date: December 2018
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020
Completion Date: January 2022

Construction

Start Date: May 2022
Projected Completion Date: November 2023
Completion Date: April 2024

Understand how we build parks.

Funding

Total Funding: $6,506,000
Funding Sources:
  • Borough President
  • City Council

Location

Fidler-Wyckoff House Park, Brooklyn
Ralph Avenue, Ditmas Avenue and Clarendon Road.
Community Board: 17

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024