Wyckoff House Park Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a public restroom building in Wyckoff House Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2017
Projected Completion Date:
December 2018
Completion Date:
January 2020
Procurement
Start Date: January 2020
Projected Completion Date:
October 2020
Completion
Date:
January 2022
Construction
Start Date: May 2022
Projected Completion Date:
November 2023
Completion Date: April 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Fidler-Wyckoff House Park, Brooklyn
Ralph Avenue, Ditmas Avenue and Clarendon Road.
Community Board: 17
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024