Queens Street Tree Planting FY13 - Community Boards 10,12-14

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant trees in Community Boards 10 & 12-14 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2012
Projected Completion Date: December 2012
Completion Date: July 2012

Procurement

Start Date: July 2012
Projected Completion Date: April 2013
Completion Date: March 2013

Construction

Start Date: September 2013
Projected Completion Date: August 2014
Completion Date: August 2014

Understand how we build parks.

Funding

Total Funding: $1,252,000
Funding Sources:
  • City Council
  • Mayoral

Location

Various Locations, Queens

Project Staff

Contact NYC Parks about this project